Retainage Tracker
Application 9 asks for $544,800.00; $326,700.00 is supported, so $218,100.00 is held, including a $31,050.00 retainage release requested before substantial completion.
D + E + F = $380,000.00 + $96,000.00 + $0.00 = $476,000.00, but column G shows $486,000.00, which carries into % and H. The overstatement of $10,000.00 less the $1,000.00 retainage on it (10.00%) = $9,000.00 comes off the payment.
Method1G703 arithmetic per line: G = D + E + F, % = G / C, H = C - G, checked against the columns as submitted ($1.00 and 0.05 point tolerance).
2G702 arithmetic: 3 = 1 + 2, 5 = 5a + 5b less any release, 6 = 4 - 5, 8 = 6 - 7, 9 = 3 - 6; line 4 against the column G total and 5a + 5b against the column I total.
| Ref | Description | Issue |
|---|---|---|
| G703 line 5 | HVAC ductwork | Arithmetic error |
| G702 line 9 | Balance to Finish, Including Retainage | Arithmetic error |
| G703 line 4 | Sanitary waste and vent piping | Line over 100% complete |
AIA G703 continuation sheet lines and G702 summary figures
Corrected pay application schedule and a release hold notice (Retainage release hold notice, Corrected G703 schedule (CSV), Corrected G702 summary (CSV))
$2,000 / month, 30% to the referring partner
Read in memory for the session, never stored, never used to train a model.
Letters, notices and legal analysis are drafts, not legal advice. Have a qualified lawyer review them before they are sent or relied on.